Getting a Building Permit for a New Home in St. Petersburg: What Goes in the Package and How Long It Takes
What the City of St. Petersburg asks for in a new-home permit package, how its ePlan review works, and how long Florida law gives it to decide.

Who issues the permit, and where you apply
Inside the city limits, building permits come from the City of St. Petersburg's Construction Services and Permitting Division, in the Municipal Services Center at One 4th Street North (727-893-7231; ePlan help desk 727-893-7230). Some beach towns, such as Madeira Beach, run their own building departments and portals, and unincorporated areas such as Tierra Verde go to Pinellas County, so check which one your lot is in first.
A new home is applied for online, through the City's permit portal (Click2Gov). Since November 1, 2023 the request for electronic plan review is made there as well, and the application number comes back right away. The City then sends an invitation to its ePlan system, where the plans and documents are uploaded and reviewed. The City has announced the move to a new Tyler software system; as of this writing, applications still go through the same portal.
What goes in the package
The City's ePlan checklist for a new single-family residence lists what has to be in the first upload. Here is how it lines up, and who prepares each part:
| Document | Who prepares it | What the City looks for |
|---|---|---|
| Building permit application | The contractor; signed and notarized, or with the City's Electronic Signature Affidavit | Every field filled in, and the construction value of each trade on page 2, the roof included |
| Survey | A Florida licensed surveyor | The lot as it is: boundary, existing grades and floor levels, including next to the lot |
| Site plan, with landscape and drainage | The designer; a civil engineer for drainage where needed | Setbacks on all sides, paving in the front yards, the A/C pad and its screening, the trees to stay and to go, a landscape plan with irrigation, the drainage plan |
| Architectural plans | The designer | Room uses and sizes, egress, stairs, elevations with heights from grade (and from the design flood elevation in a flood zone), wall sections |
| Structural plans | The engineer of record, signed and sealed | Wind speed and exposure, design loads, foundation, framing, lintels, connectors and their uplift |
| Truss package | The truss maker's engineer, approved by the engineer of record | A layout that matches the foundation and floor plans, uplift at every bearing point |
| Energy calculations | An energy preparer | Florida Energy Code forms; insulation that matches the wall section |
| Air-conditioning load calculation (Manual J) | The energy preparer or the mechanical contractor | Equipment sized to 100 to 115% of the home's cooling load |
| Florida Product Approvals | The manufacturers; we collect them | Every window, door, garage door, roof covering, soffit, siding and skylight |
| Window and Door Compliance Form, Residential Zoning Compliance Form | The contractor and the designer | The City's own forms, filled in from the plans |
Every sheet has to be digitally signed and sealed, and the City checks the signature through a third-party service. Removing a protected tree takes its own tree removal permit. A product approval only counts if the product goes in the way the approval shows; for windows, that is the subject of how we install windows in a Florida stucco home.
On a lot in a flood zone, the plans also show the flood zone and the design flood elevation, the flood vents with their calculation, and the flood-resistant materials below the floor. Remodeling an older house in a flood zone instead? The City first checks whether the work crosses its 49% line; see St. Petersburg's 49% rule.
How the review works
- Apply online. The application, with the value of each trade, goes in through the City's portal and gets its number at once.
- Upload. The City's ePlan system sends an invitation, and the plans and documents go into its folders, named the way the City's guide asks.
- Prescreen. Staff check that the upload is complete. Florida law gives the City 5 business days to say in writing what is missing; otherwise the application counts as complete.
- Review. Building, zoning and the other reviewers each read the plans and post their comments. On our most recent new home, address assignment had its own review as well.
- Respond and resubmit. Every comment is answered in a narrative letter, the changes are clouded on the sheets, and the corrected files go back in under the same file names.
- Approval. When every reviewer has approved, the fees are paid and the permit and its placard are printed for the job site.
You can follow each reviewer in the portal: select the permit, enter the application number and open the plan tracking status. For a design that is well along, the City also offers an optional preliminary plan review meeting; the drawings and questions go in at least 7 business days ahead, and its fee is credited to the permit fee.
How long it takes
Florida law sets the clock (section 553.792 of the Florida Statutes), in business days:
| Step | The limit in Florida law |
|---|---|
| The City says what is missing from the application | 5 business days, or the application counts as complete |
| The City approves, approves with conditions or denies a complete application: home under 7,500 sq ft | 30 business days |
| The same for a home of 7,500 sq ft or more | 60 business days |
| You answer the City's written comments | 10 business days, or the application is denied |
| The City approves or denies your revisions | 10 business days |
If the City misses a deadline, the law cuts the permit fee: 10% for each business day late on the first review and 20% a day on revisions, unless the delay is the applicant's or both agree in writing to more time. The City can't make you waive these deadlines to get your application reviewed.
With one round of comments, the law's limits add up to about 11 weeks of business days. Our most recent new home in the City, in 2026: we applied on March 5 and uploaded the plans the next day; the building reviewer's comments came 3 business days after the upload, zoning's after 13. We answered both and resubmitted, and the permit was approved that summer.
So plan on three to six months for the permit itself. Each extra round of comments adds weeks.
What slows a permit down
Two kinds of comments cost time: missing paperwork, and changes to the design.
The City publishes its own list of the most common reasons a residential submittal is turned down. Most of them are paperwork:
- A site plan or survey missing, or not dimensioned.
- No landscape plan.
- The application not signed, or the owner's information missing.
- The A/C unit not shown on the site plan.
- Plans not signed and sealed.
- The contractor's information not current in the City's system.
- At resubmittal, no narrative of what changed.
The comments that change the design take longer. On our own permits we have answered comments like these:
- A garage joined to the house by a breezeway counted as a separate building, because the walls between them were not continuous.
- Paving over the zoning district's limit for the lot, and in the front yard on its own.
- A side setback that depends on how high the roof starts, not only on the wall.
- Grass pavers in the front yard, and a front walk wider than the code allows.
- The electrical service size missing from the application, and the air-conditioning load calculation missing from the upload.
None of these is unusual. Each one is cheaper to settle on the first drawing than after the first review.

After the permit: roof, Notice of Commencement, inspections
Since November 1, 2025, every new home in the City gets a separate roof trade on its permit. The application carries a value for the roof on page 2, the roofer is named on a Subcontractor Job Card, and the roof inspections are scheduled under that trade. A builder can name itself for the roof when its license covers the work.
Before the first inspection, the Notice of Commencement is recorded with the Pinellas County Clerk and a copy is filed with the City. Florida law requires it when the direct contract is over $5,000, and the City won't inspect until it has the copy. It is not needed to get the permit, and it expires a year after it is recorded unless it names another date. If the home is financed, the law tells owners to talk to their lender or an attorney before recording it.
The City lists the minimum inspections for a new block home. In order:
- Foundation and slab, with the plumbing, electrical and mechanical work under the slab.
- In a flood zone (any zone but X), the elevation certificate before the walls go up: the City has to approve it before any other inspection.
- Lintel and tie beam, sheathing, and for a tile roof, the roof in progress.
- Every trade's rough-in, then framing once the house is dried in, then insulation.
- The finals of every trade, the driveway, the roof final, and a blower door test showing 5 air changes an hour or less; in a flood zone, the final elevation certificate before the building final.
- The building final, and then the Certificate of Occupancy before anyone moves in.
In a flood zone, the Non-Conversion Agreement for the space below the flood elevation is recorded with the deed, so later owners know its limits.
Fees
The City's permit fees are set in its code (section 12-6), the application states the construction value of each trade, and a plan review fee is paid early, at the ePlan stage. The only impact fee the City collects is the multimodal impact fee for transportation, set by the countywide ordinance; replacing a house earns a credit for the highest earlier use of the lot since June 30, 1986. For what permits, impact fees and surveys have come to on our own homes, see what it costs to build a custom home in St. Petersburg.
How we handle a permit
Our permits are applied for under my license as a Florida Certified Building Contractor, and I keep the permit and inspection record of every home.
We start with the lot, not the house. The survey, the zoning numbers and the flood zone go on the first sheet in our feasibility study, before anyone draws. The design is drawn to those numbers; then come the engineer of record, the energy and load calculations and the truss package, and a check of the whole package against the City's checklist before we upload it. Every comment is answered inside the City's 10 business days.
If you own a lot in St. Petersburg, or you're about to buy one, book a consultation and bring the address. We'll tell you what the City will look at first. From all of us at MTBH Studios, happy Thanksgiving.
Questions and answers
How long does a building permit for a new home take in St. Petersburg?
Florida law gives the City 30 business days to approve or deny a complete application for a home under 7,500 square feet (60 for larger homes), and 10 business days for each set of revisions. With comments to answer, plan on three to six months.
How do I check the status of a permit application?
In the City's online permit portal: select the permit, enter the application number and open the plan tracking status, which shows each reviewer's status. The ePlan help desk is at 727-893-7230.
Does a new home need a separate roof permit?
Not a separate permit. Since November 1, 2025, the City adds a separate roof trade to every new-home permit, with its own value on the application, a Subcontractor Job Card and its own inspections.
When is the Notice of Commencement recorded?
Before the first inspection, not before the permit. Florida law asks for a copy on file with the City when the direct contract is over $5,000, and the City won't inspect until it has it.
Can a private provider speed up the review?
Florida law lets an owner or contractor use a private provider for plan review and inspections. In St. Petersburg, the City's own staff still review zoning, flood, site and drainage, and the provider's certificate of compliance is needed before the Certificate of Occupancy.
Can I look up a property's permit records?
The City's online permit portal has its permit list, the City's Property Cards database shows a property's certificates of occupancy for free, and elevation certificates on file since 1990 can be searched online.
Do small repairs need a permit?
Since July 1, 2026, the City has a permit exemption form for work on a single-family home under $7,500, but only outside flood hazard areas and only for work with no structural, window, door, roofing, siding, mechanical, electrical, plumbing or gas work.
Sources: City of St. Petersburg, Building & Permitting (separate roof trade from November 1, 2025; the new Tyler software system; hours and phones), read November 12, 2026; City of St. Petersburg, Building Permits (ePlan submittal process, plan tracking, preliminary plan review, inspections, certificates, HB 803 exemption), read November 12, 2026; City of St. Petersburg, ePlan Submittal Checklist, Residential NSFR Project Permit, read November 12, 2026; City of St. Petersburg, Residential Plans Submittal Checklist (revised March 19, 2021), read November 12, 2026; City of St. Petersburg, Roof Trade Update (effective November 1, 2025), read November 12, 2026; City of St. Petersburg, Inspection Requirements NSFR/Additions, Block Wall, read November 12, 2026; City of St. Petersburg, Fees (permit and impact fees), read November 12, 2026; Florida Statutes 553.792, building permit application to local government (timeframes), 2026, read November 12, 2026; Florida Statutes 713.135, notice of commencement and applicability of lien, 2026, read November 12, 2026; Florida Statutes 713.13, notice of commencement (form and expiration), 2026, read November 12, 2026; Florida Statutes 553.791, alternative plans review and inspection (private providers), 2026, read November 12, 2026; Florida Statutes 553.842, product evaluation and approval, 2026, read November 12, 2026